J&M Steel completed 2 expansions for FedEx at the North Salt Lake facility.
The first addition was completed in 2005 on the north end of the building consisting of 30,000 square feet.
In 2008 J&M added 46,000 square feet to the south side of the building.
Both additions were complex and involved tying 3 buildings together.
The projects were also completed in winter conditions, ahead of schedule, and while FedEx continued its day-to-day operations.