J&M Steel worked through one of the worst winters with the most precipitation Utah has had in years and still hit all the milestones & completed the project on-time. Due to the tight schedule J&M Steel built the joist and deck into kits on a jig and stockpiled them for future use. Building these kits allowed us to maintain and hit and critical path schedule items.
J&M Steel participated in daily coordination meeting with the General Contractor & conducted daily safety meetings.
Our Project Manager worked closely with the contractor & design team to ensure we had the latest approved drawings. We then pass this information onto our field superintendent & foreman’s to be built per plans & specs from these latest approved drawings.
J&M Steel worked closely with Big D to design and maintain the budget & constructability of the building.
The work was performed during the middle of winter with some extreme weather conditions. J&M Steel complied with all the safety regulation throughout the entire project.
- Architect: HWA
- Engineer: Dunn & Associates
- Type of Construction: Tilt-up / Structural Steel / Joist / Decking
- Length of Project: Steel Erection 15 Weeks Start to Finish
- Materials: Structural Steel, Joist, Decking