J&M Steel participated in daily coordination meeting with the General Contractor & conducted daily safety meetings. J&M Steel also coordinated daily with Gem Buildings for on-time deliveries.
Our Project Manager worked closely with the contractor & design team to ensure we had the latest approved drawings. We then pass this information onto our field superintendent & foreman’s to be built per plans & specs from these latest approved drawings.
The Steel Erection was completed in 13 weeks start to finish.
J&M Steel worked closely with Layton Construction & Gem Buildings to design and maintain the budget & constructability of the building.
The work was performed on an extremely tight jobsite. Therefore, the sequencing and on-time deliveries were crucial to the overall schedule of the project. J&M Steel had to coordinated closely with Gem Buildings so that only the steel that would be used that day could be delivered. J&M Steel complied with all the safety regulation on the site. J&M steel worked extra hours to turnover each floor on-time to Layton Construction for pours and other trade(s) access.
- Architect: IBI Group
- Engineer: Dunn & Associates
- Steel Fabricator: Gem Buildings
- Materials: Structural Steel, Joist, Decking